New Jersey American Water – Oak Street Project
Lakewood, New Jersery
Lakewood, New Jersery
The plant will be constructed on a T&M basis not to exceed the Guarantied Maximum Price. Job includes installing owner supplied water treatment equipment for PFAS removal. Equipment to be installed on a concrete slab and will be enclosed in a building. A backwash holding tank will also be erected and piped to the sanitary sewer.
Contract Amount:
$4,498,553
Notice to Proceed:
June 1, 2024
Est. Completion Date:
July 1, 2025
MGD: 2.88
Owner:
New Jersey American Water
Engineer:
Gannett Fleming