City of Aurora Eastern Utility Extension Zone 4 Waterline

Aurora, Colorado

Project Description

The City of Aurora has contracted with Reynolds Construction as the CMGC for the Eastern Utility Extension Zone 4 Waterline Project (‘Project”). Reynolds is acting as the procurement agent and is anticipated to self-perform the installation of the pipeline.  The Project consists of approximately 42,500 LF of 30” waterline, two(2) tunnel crossings at Interstate 70 and the Union Pacific Railroad. The Project includes mainline valves, access vaults, and approximately three(3) interconnections to existing infrastructure.

At A Glance

Contract Amount:
$33,652,780

Notice to Proceed:
August 1, 2022

Est. Completion Date:
March 31, 2025

Owner:
City of Aurora

Engineer:
HDR

Get in Touch

If we seem a little unique for a construction company, we’ll take it as a compliment. We’d love to talk about what it be like to work together, the way we both want to.